Projects Description Location Type OWNER CLIENT Period
Start Finish
Maintenance Work and Assistance Service in Mechanical & Operation Areas for TEL Pulp & Paper Plant Musi - Palembang, South Sumatera - Indonesia Maintenance PT. Tanjung Enim Lestari Pulp & Paper PT. Tanjung Enim Lestari Pulp & Paper Apr-06 Continued
Maintenance Work for INCO Nickel Mining Plant Soroako, South Sulawesi - Indonesia Maintenance PT. International Nickel Indonesia PT. International Nickel Indonesia Oct-06 Continued
Maintenance Work for RAPP, IKPP Pulp & Paper Plant Kerinci, Riau, Indonesia Maintenance PT. RAPP PT. RAPP Oct-06 Continued
Pelabuhan Ratu 3 X 330 MW Coal Fired Steam Power Plant Pelabuhan Ratu, West Java - Indonesia Construction PT. PLN Shanghai Electric Corporation / PT. Maxima Infrastructure Aug-07 Feb'13
Indramayu 3 X 330 MW Coal Fired Steam Power Plant Indramayu, West Java - Indonesia Construction PT. PLN China National Electric Equipment Corporataion Nov-07 Dec'11
Muara Karang Gas Power Plant Repowering 675-775 MW Muara Karang, Jakarta - Indonesia Construction PT. PLN Mitsubishi Corporation Dec'07 Apr-11
Suralaya 1 X 600 MW Coal Fired Steam Power Plant Suralaya, Banten - Indonesia Construction PT. PLN China National Technical Import & Export Corporation Jan-08 May-11
EPC Work for Earth Work, Foundation, Pipe Piling, Sheet Piling, Structure, Building, Pipe Rack, Canal, Road Class A, B, C, Bridges, Fencing, Pipe Support, Piping, Mechanical, Electrical, Instrument for 533 Well and 3 No's Station NDD Area-12 Surface Facility Duri, Riau - Indonesia EPC PT. Chevron Pacific Indonesia PT. Chevron Pacific Indonesia Feb'08 Jan-11 Continued to for Maintenance Period
Replacement and Refurbishment Work of Boiler Units 1 & 2 for Rehabilitation And Upgrade of Suralaya SPP Unit 1 - 4 (4 X 400 MW) Suralaya, Banten - Indonesia Construction PT. PLN Marubeni Corporation Dec'08 Dec-11
Maintenance Work for Holcim Cement Plant Cibinong, West Java - Indonesia Maintenance PT. Holcim Indonesia, Tbk PT. Holcim Indonesia, Tbk Jan-09 Continued
Tanjung Jati "B" Mechanical Erection Boilers & Aux Equipment for 2 X 660 MW Coal Fired Steam Power Plant Expansion Units 3 & 4 Tanjung Jati - Jepara, West Java - Indonesia Construction PT. Central Java Power PT. Jurong Engineering Lestari Jul-09 Oct'11
Paiton Unit-3 800 MW Coal Fired Steam Power Plant Paiton, East Java - Indonesia Construction PT. Paiton Energy Taihei Dengyo Kaisha, LTD. Nov-09 Nov-11
Tanjung Jati "B" Boilers BOP Erection (Ship Unloader, Stacker Reclaimer, FGD, ESP, Coal & Ash Handling System) for 2 X 660 MW Coal Fired Steam Power Plant Expansion Units 3 & 4 Tanjung Jati - Jepara, West Java - Indonesia Construction PT. Central Java Power Sumitomo Corporation. ED Jan'10 Aug-11
Maintenance Work (Manpower & Equipment Supply) for Tangguh LNG Plant Tanah Merah, Papua - Indonesia Maintenance PT. BP Indonesia PT. JGC / PT. KBR Consortium Jan-10 Continued
Muara Tawar Gas Fired Power Plant Extension MT-5 Muara Tawar - Bekasi, West Java - Indonesia Construction PT. PLN PT. Jurong Engineering Lestari Feb-10 Oct'11
Tanjung Jati "B" Turbine Generators Installation (Critical Piping, STG Piping Condenser & LP Heater) for 2 X 660 MW Coal Fired Steam Power Plant Expansion Units 3 & 4 Tanjung Jati - Jepara, West Java - Indonesia Construction PT. Central Java Power PT. Jurong Engineering Lestari Feb-10 Oct'11
Long Term Construction Service Work Unit Rate Package "C" Duri, Riau - Indonesia Construction PT. Chevron Pacific Indonesia PT. Chevron Pacific Indonesia Mar-10 Mar-14
Replacement and Refurbishment Work of Steam Turbine and Generator Units 1 & 2 for Rehabilitation And Upgrade of Suralaya SPP Unit 1 - 4 (4 X 400 MW) Suralaya, Banten - Indonesia Construction PT. PLN Mitsubishi Heavy Industries May-10 Apr-11
Civil, Structural & Mechanical Work for Overland Conveyor & Coal Terminal for KPC Coal Mining Expansion Sanggata, East Kalimantan - Indonesia Construction PT. Kaltim Prima Coal PT. Robert Schaefer Soros Indonesia Jun-10 Dec-11
EPC Work for Buntok 2x7 MW Coal Fired Power Plant Buntok, Kalimantan, Indonesia EPC PT. PLN PT. PLN Dec-10 Oct'12
Mechanical Erection (8,424 Ton) for 2x60 MW Sulfindo Power Plant Merak, Banten - Indonesia Construction PT. Merak Energy Daewoo Engineering Company Apr-11 Nov'12
Electrical Furnice #2, Rotary Kiln #3 Rotary Kiln#1 Rebuil Main Construction Soroako, South Sulawesi - Indonesia Construction PT. International Nickel Indonesia PT. International Nickel Indonesia Jun-11 Apr-12
EPC Work for Lime Calcining Plant II Project Turnkey Pproject - Consortium With Maerz of Enbau AG Cilegon, Banteni - Indonesia EPC PT. Krakatau Steel PT. Krakatau Steel Jul-11 Sep-12
Turnkey Overhoul Boiler Unit 3 Cilegon, Banten - Indonesia Construction PT. Krakatau Daya Listrik PT. Krakatau Daya Listrik Jul-11 Nov-11
Structural Mechanical Erection Work For KPC1 Coal Mining Expansion Melawan, East Kalimantan - Indonesia Construction PT. Kaltim Prima Coal PT. Robert Schaefer Soros Indonesia Oct-11 Sep-12

 