Below is the list of TJE's ongoing project.
| Projects Description |
Project Type |
CLIENT |
Period |
| Start |
Finish |
| Installaion Construction Work 1x660 MW CFSPP , Paiton, East Java |
Construction |
Beijing Electric Power Construction Company (BEPCC) |
May-08 |
Jan-10 |
| CP Bahari Power Plant, (2x30 MW) CFSPP |
Construction |
Manunggal Egineering |
Jul-08 |
May-09 |
| Tanjung Jati - B, 2x660 MW, CFPP, Installation of CW Pipe, Central Java |
Construction |
Sumitomo Corp. Erection Division |
Feb-09 |
Mar-10 |
| Tanjung Jati - B, 2x660 MW ,CFPP, Mechanical Erection of Boilerand Auxiliary Equipment, Central Java |
Construction |
P.T Jurong Engineering Lestari |
Oct-09 |
Aug-11 |
| Paiton Unit 3 - 800 MW, Expansion Project, Paiton East Java |
Construction |
Taeihei Dengyo Kaisha, Ltd |
Nov-09 |
Nov-11 |
| Tanjung Jati - , 2x660 M, CFPP Expansion Project - Seel Structure Erection & Field Painting of Turbine & Control Building |
Construction |
MES-TSW Joint Operation (Mitsui Engineering & Shipbuilding Co, .Ltd |
Jun-09 |
Aug-10 |
| 2x660 MW Steam Power Plant : Boiler & BOP Turbine, Tj. Jati-B |
Construction |
P.T. PLN |
Aug-03 |
Continue-Commissioning |
| Tarahan 2x100 MW Unit 3&4 Coal Fired Steam Power Plant Project |
Construction |
P.T. Jurong Engineering Lestari |
Jun-05 |
Continue-Commissioning |
| Mechanical Equipment Erection Work - Tangguh LNG |
Construction |
JGC / KBRI |
Jul-06 |
Jul-08 |
| Upgrading Brown Coal (UBC) Project - Civil and Building Work & Mechanical and Electrical |
Construction |
Kobe Steel Ltd |
Apr-07 |
Nov-08 |
| INCO, Off Gas Cleaning General Construction & Installation |
Construction |
P.T. INCO |
Sep-06 |
Continue-New Package/Additional |
| Construction Service for Abandonment and Remediation Project, Duri |
Construction |
Tripatra - Flour |
Apr-07 |
Apr-08 |
| Maintenance and Assistance Service in Mechanical & Operation Areas, TEL, MUSI |
Maintenance |
P.T. Tanjung Enim Lestari |
Apr-06 |
Apr-08 |
| Flexible Program Management, Maintenance & Construction Service, Duri, Riau |
Maintenance |
Tripatra - Flour |
Dec-05 |
Dec-07 |
| Flexible Program Management, Maintenance & Construction Service, Minas, Riau |
Maintenance |
Tripatra - Flour |
Dec-05 |
Jun-08 |
| Maintenance Works of RAPP and Miscelaneous Work of IKPP (Fabr. & Erection New Reclaimer Boom) |
Maintenance |
P.T. RAPP / P.T. IKPP |
Oct-06 |
Apr-07 |
| PLTU 2 Banten (2x300 MW) Coal Fired Steam Power Plant |
Construction |
Chengda Engineering Corporation of China |
Mar-07 |
Dec-09 |
| Early Earth Work and Civil Work of Kilin Scope North Duri Development |
Construction |
Tripatra - Flour |
Jun-07 |
Continue-New Package/Additional |
| GIIC Pellet Plant Mechanical Erection Work Plus Steel Structure Supply and Works, Bahrain |
Construction |
Kobe Steel Ltd |
Aug-07 |
May-09 |
| Muara Karang Gas Power Plant Project (Repowering) |
Construction |
Mitsubishi Corporation |
Sep-07 |
Apr-10 |
| PLTU Pelabuhan Ratu 3x300 MW |
Civil, Construction |
Shanghai electric Corporation - P.T. Maxima Infarstruktur |
Nov-07 |
Nov-10 |
| Steel Components Fabrication (Package A & C) for GIIC Pellet Plant, Bahrain |
Construction, Fabrication |
Kobe Steel Ltd |
Nov-07 |
Nov-08 |
| Work of MEI Installation PLTU 3x330 MW, Indramayu |
Construction |
China National Electric Equipment Corporation (CNEEC) |
Nov-07 |
Mar-10 |
| Sengkang Private Power Expansion 1x60 MW GTPP Project |
EPC |
P.T. Energy Sengkang |
Nov-07 |
Nov-08 |