Below is the list of TJE's ongoing project.
| Projects Description |
Location |
Type |
OWNER |
CLIENT |
Period |
| Start |
Finish |
| Maintenance Work and Assistance Service in Mechanical & Operation Areas for TEL Pulp & Paper Plant |
Musi - Palembang, South Sumatera - Indonesia |
Maintenance |
PT. Tanjung Enim Lestari Pulp & Paper |
PT. Tanjung Enim Lestari Pulp & Paper |
Apr-06 |
Continued |
| Maintenance Work for INCO Nickel Mining Plant |
Soroako, South Sulawesi - Indonesia |
Maintenance |
PT. International Nickel Indonesia |
PT. International Nickel Indonesia |
Oct-06 |
Continued |
| Maintenance Work for RAPP, IKPP Pulp & Paper Plant |
Kerinci, Riau, Indonesia |
Maintenance |
PT. RAPP |
PT. RAPP |
Oct-06 |
Continued |
| Pelabuhan Ratu 3 X 330 MW Coal Fired Steam Power Plant |
Pelabuhan Ratu, West Java - Indonesia |
Construction |
PT. PLN |
Shanghai Electric Corporation / PT. Maxima Infrastructure |
Aug-07 |
Feb'13 |
| Indramayu 3 X 330 MW Coal Fired Steam Power Plant |
Indramayu, West Java - Indonesia |
Construction |
PT. PLN |
China National Electric Equipment Corporataion |
Nov-07 |
Dec'11 |
| Muara Karang Gas Power Plant Repowering 675-775 MW |
Muara Karang, Jakarta - Indonesia |
Construction |
PT. PLN |
Mitsubishi Corporation |
Dec'07 |
Apr-11 |
| Suralaya 1 X 600 MW Coal Fired Steam Power Plant |
Suralaya, Banten - Indonesia |
Construction |
PT. PLN |
China National Technical Import & Export Corporation |
Jan-08 |
May-11 |
| EPC Work for Earth Work, Foundation, Pipe Piling, Sheet Piling, Structure, Building, Pipe Rack, Canal, Road Class A, B, C, Bridges, Fencing, Pipe Support, Piping, Mechanical, Electrical, Instrument for 533 Well and 3 No's Station NDD Area-12 Surface Facility |
Duri, Riau - Indonesia |
EPC |
PT. Chevron Pacific Indonesia |
PT. Chevron Pacific Indonesia |
Feb'08 |
Jan-11 Continued to for Maintenance Period |
| Replacement and Refurbishment Work of Boiler Units 1 & 2 for Rehabilitation And Upgrade of Suralaya SPP Unit 1 - 4 (4 X 400 MW) |
Suralaya, Banten - Indonesia |
Construction |
PT. PLN |
Marubeni Corporation |
Dec'08 |
Dec-11 |
| Maintenance Work for Holcim Cement Plant |
Cibinong, West Java - Indonesia |
Maintenance |
PT. Holcim Indonesia, Tbk |
PT. Holcim Indonesia, Tbk |
Jan-09 |
Continued |
| Tanjung Jati "B" Mechanical Erection Boilers & Aux Equipment for 2 X 660 MW Coal Fired Steam Power Plant Expansion Units 3 & 4 |
Tanjung Jati - Jepara, West Java - Indonesia |
Construction |
PT. Central Java Power |
PT. Jurong Engineering Lestari |
Jul-09 |
Oct'11 |
| Paiton Unit-3 800 MW Coal Fired Steam Power Plant |
Paiton, East Java - Indonesia |
Construction |
PT. Paiton Energy |
Taihei Dengyo Kaisha, LTD. |
Nov-09 |
Nov-11 |
| Tanjung Jati "B" Boilers BOP Erection (Ship Unloader, Stacker Reclaimer, FGD, ESP, Coal & Ash Handling System) for 2 X 660 MW Coal Fired Steam Power Plant Expansion Units 3 & 4 |
Tanjung Jati - Jepara, West Java - Indonesia |
Construction |
PT. Central Java Power |
Sumitomo Corporation. ED |
Jan'10 |
Aug-11 |
| Maintenance Work (Manpower & Equipment Supply) for Tangguh LNG Plant |
Tanah Merah, Papua - Indonesia |
Maintenance |
PT. BP Indonesia |
PT. JGC / PT. KBR Consortium |
Jan-10 |
Continued |
| Muara Tawar Gas Fired Power Plant Extension MT-5 |
Muara Tawar - Bekasi, West Java - Indonesia |
Construction |
PT. PLN |
PT. Jurong Engineering Lestari |
Feb-10 |
Oct'11 |
| Tanjung Jati "B" Turbine Generators Installation (Critical Piping, STG Piping Condenser & LP Heater) for 2 X 660 MW Coal Fired Steam Power Plant Expansion Units 3 & 4 |
Tanjung Jati - Jepara, West Java - Indonesia |
Construction |
PT. Central Java Power |
PT. Jurong Engineering Lestari |
Feb-10 |
Oct'11 |
| Long Term Construction Service Work Unit Rate Package "C" |
Duri, Riau - Indonesia |
Construction |
PT. Chevron Pacific Indonesia |
PT. Chevron Pacific Indonesia |
Mar-10 |
Mar-14 |
| Replacement and Refurbishment Work of Steam Turbine and Generator Units 1 & 2 for Rehabilitation And Upgrade of Suralaya SPP Unit 1 - 4 (4 X 400 MW) |
Suralaya, Banten - Indonesia |
Construction |
PT. PLN |
Mitsubishi Heavy Industries |
May-10 |
Apr-11 |
| Civil, Structural & Mechanical Work for Overland Conveyor & Coal Terminal for KPC Coal Mining Expansion |
Sanggata, East Kalimantan - Indonesia |
Construction |
PT. Kaltim Prima Coal |
PT. Robert Schaefer Soros Indonesia |
Jun-10 |
Dec-11 |
| EPC Work for Buntok 2x7 MW Coal Fired Power Plant |
Buntok, Kalimantan, Indonesia |
EPC |
PT. PLN |
PT. PLN |
Dec-10 |
Oct'12 |
| Mechanical Erection (8,424 Ton) for 2x60 MW Sulfindo Power Plant |
Merak, Banten - Indonesia |
Construction |
PT. Merak Energy |
Daewoo Engineering Company |
Apr-11 |
Nov'12 |
| Electrical Furnice #2, Rotary Kiln #3 Rotary Kiln#1 Rebuil Main Construction |
Soroako, South Sulawesi - Indonesia |
Construction |
PT. International Nickel Indonesia |
PT. International Nickel Indonesia |
Jun-11 |
Apr-12 |
| EPC Work for Lime Calcining Plant II Project Turnkey Pproject - Consortium With Maerz of Enbau AG |
Cilegon, Banteni - Indonesia |
EPC |
PT. Krakatau Steel |
PT. Krakatau Steel |
Jul-11 |
Sep-12 |
| Turnkey Overhoul Boiler Unit 3 |
Cilegon, Banten - Indonesia |
Construction |
PT. Krakatau Daya Listrik |
PT. Krakatau Daya Listrik |
Jul-11 |
Nov-11 |
| Structural Mechanical Erection Work For KPC1 Coal Mining Expansion |
Melawan, East Kalimantan - Indonesia |
Construction |
PT. Kaltim Prima Coal |
PT. Robert Schaefer Soros Indonesia |
Oct-11 |
Sep-12 |