PT. Truba Jaya Engineering has established its presence in Southeast Asia and the Middle East through cooperation agreements or Partnership with reputable local companies. Together with the partners, total project execution is carried out with direct access to local facilities, providing administrative support and assurance that the projects are delivered according to client's requirements, on time and on budget.
PT. Truba Jaya Engineering can tap its exiting well-trained pool of skilled manpower from Indonesia as well as from exclusive resource base from Asian countries such as India, Bangladesh, Pakistan, Philippines, and Nepal that are ready to support our operations. Construction equipment and machineries can be mobilized from available local sources, reputable international sources or from our own equipment pool in Indonesia and Singapore.
Anywhere the project is, PT. Truba Jaya Engineering brings its proven project management systems based on internationally recognized quality assurance ISO 9000-2000, The National Board of Boiler and Pressure Vessel Inspectors (NBIC "R"), The American Society of Mechanical Engineers (ASME "S") , SMK3, OHSAS 18001, ISO 14001 and well-trained key staff from Home Office and sister companies that can tackle any from of Power and Industrial project of clients in the Middle East.
| Name of Project |
Size |
Make |
Location |
Scope |
Client/Owner |
Schedule |
| CPS Extension Project |
150 MW |
3 Units GE Frame 7E GT |
Asir, Jizan Tihama |
Electro Mechanical installation of Gas Turbines & auxilliaries |
Arabian Bemco/SEC |
Jan 2002 - Nov 2002 |
| CPS Extension Project |
150 MW |
3 Units GE Frame 7E GT |
Asir, Jizan Tihama |
Electro Mechanical installation of Gas Turbines & auxilliaries |
Arabian Bemco/SEC |
Jan 2003 - Nov 2003 |
| Al Safi Danone Integrated Dairy Plant Expansion project |
Various |
GEA Tuchenhagen |
Al Kharj |
Mechanical Eqpuiment & piping Installation. New Dairy Plant, Milk & Laban Project ,Tornado-2 |
GEA Tuchenhagen/Al Safi Danone |
Mar 2003 - Dec2003 Mar 2004 -Sep 2004 Sep 2004 - Feb 2005 |
| Al SAFA Substation |
110 KV GIS |
TOSHIBA |
Al Safa |
Electro Mechanical Installation (Indoor & Outdoor) |
Arabian Bemco/SEC |
Oct 2003 - Oct 2003 |
| Khaybar Substation |
110 KV AIS |
|
Khaybar |
Electro Mechanical Installation (Indoor & Outdoor) |
Arabian Bemco/SEC |
Oct 2003 - Oct 2003 |
| PP-9 Power Plant Block'E' Ultra Fast Track Project |
400 MW |
8 Units GE Frame 7E GT |
|
Electro Mechanical installation of Gas Turbines inclusive auxilliaries |
Arabian Bemco/SEC |
Mar 2004 - Sep 2004 |
| Tabouk Power Plant Expansion Project |
100 MW |
2 Units GE Frame 7E GT |
Tabouk |
Electro Mechanical installation of Gas Turbines inclusive auxilliaries |
Arabian Bemco/SEC |
Feb 2004 - Nov 2004 |
| Sadaf Cogeneration Plant Project |
200 MW |
2 Units Siemens - Westinghouse |
Jubail |
Electro Mechanical installation of Gas Turbines. |
Arabian Bemco/Siemens/Sadaf |
Mar 2004 - Dec 2004 |
| Madina Bulk Plant Project |
various |
various |
Madina |
Installation of piping,mechanical equipment & electrical |
Arabian Bemco/Saudi Aramco |
Sep 2004 - Aug 2006 |
| King Abdul Aziz University Chiller Plant Link Piping Project |
various |
various |
Jeddah |
Installation of Under ground & above Ground Pipes |
Arabian Bemco/King Abdul Aziz University |
Aug 2004 - Mar 2005 |
| PP-7 Riyadh |
200 MW |
2 Units Siemens |
Riyadh |
Electro Mechanical installation of Gas Turbines |
Arabian Bemco/SEC/Siemens |
Nov 2004 - Jul 2005 |
| Najran CPS Extension Unit 9 |
50 MW |
1 Unit GE Frame 7E GT |
Najran |
Electro Mechanical installation of Gas Turbines |
Arabian Bemco/SEC |
Jan 2006 - Aug 2006 |
| Shoaiba Stage II ,Phase-I, Units 9,10, 11 |
1,110 MW |
3 Units Alstom/ABB |
Shoaiba |
3 x 370 MW Power Block & Steam Turbine inclusive of all Mech.,Piping Instrumentation,Painting & Insulation |
Alstom Power Centrale France/SEC |
Jan 2005 - Dec 2006 |
| Shoaiba Stage II , Phase-II, Units 6,7,8 |
1,110 MW |
3 Units Alstom/ABB |
Shoaiba |
3 x 370 MW Power Block & Steam Turbine inclusive of all Mech.,Piping Instrumentation,Painting & Insulation |
Alstom Power Centrale France/SEC |
Mar 2006 - Dec 2007 |
| Hail - Unit 6 |
50 MW |
1 Unit GE Frame 7E GT |
Hail |
Electro Mechanical installation of Gas Turbines & auxilliaries |
Arabian Bemco/SEC |
Dec 2006 - Jun 2007 |
| PP-9 Block C & D Power Plant |
800 MW |
16 Unit GE Frame 7E GT |
Riyadh |
Mechanical & Electrical installation of Gas Turbines & auxilliaries, BOP Piping |
Arabian Bemco/SEC |
July 2006 - Dec 2008 |
| Najran, Unit -10 |
50 MW |
1 Unit GE Frame 7E GT |
Najran |
Electro Mechanical installation of Gas Turbines & auxilliaries |
Arabian Bemco/SEC |
Aug 2007- Jan 2008 |
| PP-9, Block F Power Plant |
400 MW |
8 Unit GE Frame 7E GT |
Riyadh |
Mechanical installation of Gas Turbines inclusive of Auxilliaries & BOP Piping |
Arabian Bemco/SEC |
Nov 2007 - Dec 2008 |
| Qurayyah Simple Cycle Power Plant |
1800 MW |
15 Unit GE Frame 7F |
Qurayyah |
Mechanical installation of Gas Turbines inclusive of Auxilliaries & BOP Piping |
Arabian Bemco/SEC |
Nov 2007 - Oct 2010 |
| Juaymah Gas Plant |
Waste Water Spent Caustic |
Piping |
Juaymah |
Mechanical, Piping & painting Works |
Arabian Bemco/Saudi Aramco |
Aug 2008 - Jan 2009 |
| King Abdul Aziz University CUP-2 Project |
Chiller Plant |
5 Dual Mode Chillers 36 Fluid Coolers |
Jeddah |
Mechanical Works & Installation of Under ground & above Ground Pipes |
Arabian Bemco/King Abdul Aziz University |
Jan 2009 - Sep 2009 |
| PP-10 Riyadh |
1200 MW |
24 Units GE Frame 7E GT |
Riyadh |
Mechanical installation of Gas Turbines inclusive of Auxilliaries & BOP Piping |
Arabian Bemco/SEC |
Jun 2009 - Jun 2011 |
| Shoaiba Stage III Power Plant |
1100 MW |
3 Units Alstom |
Shoaiba |
3x 370 MW power block & steam turbines inclusive of all Mech, Equipment, piping Instrumentation Insulation& Painting |
Alstom Power Centrale France/SEC |
Nov 2009 - Jun 2011 |
| Qurayyah Combined Cycle Power Plant - Phase C |
1300 MW |
5 Blocks |
Qurayyah |
Erection of 5 blocks Steam Turbines, Pipings & Insulation Works |
Arabian Bemco/Doosan/SEC |
Jun 2010 - Dec 2012 |
| Qassim Power Plant Extension III |
480 MW |
8 Units GE Frame 7E GT |
Qassim |
Mechanical installation of Gas Turbines inclusive of Auxilliaries & BOP Piping |
Arabian Bemco/SEC |
July 2011 - Apr 2012 |
| PP-10 Block C1 |
240 MW |
4 Units GE Frame 7E GT |
Riyadh |
Mechanical installation of Gas Turbines inclusive of Auxilliaries |
Arabian Bemco/SEC |
Sep 2011 - Apr 2012 |
| Qurayyah Power Plant Block 6 |
620 MW |
3 Units GE Frame 7E GT 1 STG |
Qurayyah |
Erection of 3 Units GTG, 3 Units HRSG and 1 STG |
Arabian Bemco/SEC |
Aug 2011 - Nov 2012 |